Construction Progress
Bay Street Baptist Church
March 20, 2012
Schedule the movers, the new sanctuary for Bay Street Baptist Church is nearing completion!
H. J. High is now completing the installation of flooring, painting, cabinetry, and wall finishes at the new sanctuary. While this aspect of the work signals the project is almost finished, it is an even more important milestone for Bay Street. When the project commenced the church was unsure whether their budget would allow for these finishes as part of construction of the facility. H. J. High aggressively managed costs throughout the subcontract award and work execution phases, and combined with contributions by an excited and generous congregation the church was able to finish the entire build out as they had hoped. We are proud to have been able to work in close association with church leaders to build the facility they intended.
We anticipate completing final inspections in the next week and receiving a Certificate of Occupancy by the end of the month!
Construction Progress
Bay Street Baptist Church
January 25, 2012
We are entering the final months of construction at Bay Street Baptist Church. All site work and paving has been completed with the installation of the septic field finishing up. The cross was raised just before Christmas on the exterior and is easily visible from the road. Inside we have finished all framing and drywall installation allowing the painter to work on the walls and ceiling. All ductwork and lighting has been installed. The church has authorized the installation of finishes that will commence at the end of January. Bay Street Baptist will utilize a crew of volunteers to install the irrigation and landscaping beginning the first week of February.
Excitement from the congregation and community is growing as the project nears completion.
Construction Progress
Bay Street Baptist Church
November 4, 2011
The openings in the building siding panels have been cut and trimmed and the metal roof panels are now 75% complete. Inside the building, the overhead ductwork and sprinkler pipe is being installed and the walls are being laid out. For site work, the fire line and domestic water lines are being tested and the storm piping and drainage structures are complete.
Construction Progress
Bay Street Baptist Church
October 24, 2011
The building siding panels have been installed and the openings are being cut and trimmed. The framing members for the roof are being braced and the roof decking will be completed by the week of October 31st, 2011. After the roof decking is completed, rough-in of the overhead ductwork, sprinkler piping, and electrical conduits will begin. Metal stud and sheathing will begin for the tower enclosure in two weeks. The domestic water line and the fire protection water line have been installed from the roadway to the building and are being pressure tested. The storm water pipes and drainage structures are currently being installed.
Construction Progress
Bay Street Baptist Church
September 22, 2011
The building is starting to take shape! The steel building package was delivered on Thursday, September 15th and is currently being erected. The split face masonry will be delivered this week and installation will begin Monday, September 26. The metal siding was delivered Wednesday, September 21 and will be installed after the masonry is complete. The exterior door frames will be delivered and installed the week of September 26, 2011.
Construction Progress
Bay Street Baptist Church
September 8, 2011
Construction began in early July for the new Bay Street Baptist Church in Eustis, Florida. To date, the site has been cleared, one of the retention ponds has been excavated and fill has been placed for the building pad and the areas adjacent to the building.
In August, the foundations were placed, underground piping and conduit were installed for the plumbing and electrical systems and the floor slab was poured.
The Steel Building and roof deck are due to arrive and be erected beginning in mid September.
Check back weekly for updates!