Construction Progress

GCSC-June13-3

Gulf Coast State College Advanced Technology Center
June 2013

The month of June started after reaching a significant milestone on the Gulf Coast State College Advanced Technology Center: the Bay County Building Department issued the Certificate of Occupancy on May 31.

(more…)

Construction Progress

GCSC-May13-2

Gulf Coast State College Advanced Technology Center
May 2013

Work on the Gulf Coast State College Advanced Technology Center has entered the home stretch, and the last of the remaining work is getting finished up.

(more…)

Construction Progress

GCSC-Apr13-9

Gulf Coast State College Advanced Technology Center
April 2013

Work is quickly coming to an end as the main portion of the Gulf Coast State College Advanced Technology Center enters the final push.

(more…)

Construction Progress

GCSC-Mar13-1

Gulf Coast State College Advanced Technology Center
March 2013

This month the Gulf Coast State College Advanced Technology Center entered the home stretch of the project – the countdown clock passed the “90 days remaining” mark.

(more…)

Construction Progress

GCSC-Feb13

Gulf Coast State College Advanced Technology Center
February 2013

This month the highlight of work on the Gulf Coast State College Advanced Technology Center actually occurred off-site. GAC/H. J. High appeared before GCSC’s Board of Trustees to report a savings on the project of more than $600K. This savings is attributed to the solid working relationship among the college, Florida Architects, and GAC/H. J. High team members and their methodology in administering the project. The college was thrilled to be able to invest this savings into additional equipment purchases for the facility.

(more…)

Construction Progress

GCSC-Jan13-1

Gulf Coast State College Advanced Technology Center
January 2013

Work on the Gulf Coast State College Advanced Technology Center continues at a frenetic pace as the new year gets kicked off. Work on the interior finishes continues with interior painting of partitions, installation of ceramic tile in the restrooms, and the remaining drywall being hung and finished. By month’s end, the stairwells and some smaller areas of detailed work will be the only drywall work remaining. Light fixtures and HVAC ceiling diffusers are being installed where ceiling grid has been installed, and ceiling grid work continues to follow areas where walls have been painted. The raised access floor installation started late in the month and will be completed early next month.

(more…)